EMT Practice Test

1. Question Content...


Question List

Question1: The business analyst receives multiple changes from different stakeholders during the requirements gathering phase of a project. How should the business analyst track the requirements throughout the lifecycle of the project to secure the delivery of the expected solution?

Question2: A business analyst captures an application's current limitations and consults with end users to identify new features for the next version.
What can be used to analyze this information and determine project scope?

Question3: What should a business analyst do after discovering that two solution requirements conflict?

Question4: A business analyst has elicited, documented, and verified the requirements, discovering that there are not enough resources to deliver all the requirements. Which technique should the business analyst employ to rectify the issue?

Question5: A company's management team has decided to deploy a new product. However, there is concern that users may not accept a new product that forces them to change existing practices.
The business analyst should:

Question6: A company has completed a major project within time, cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment.
From the business analysis perspective, the main reason for this business failure was a failure to:

Question7: A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager. The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix.
Which of the following is the best strategy to define the appropriate acceptance criteria?

Question8: A company has just finished the development work for a new software sales tracking application and is in the process of validating that the new application meets all of the acceptance criteria defined for the business requirements. During the validation process, a stakeholder discovers that the application does not provide the selection criteria needed to produce the sales volume reporting required by the company's financial department. The business analyst for the project determines that the selection criteria needed was not specified in the system requirements or design specifications.
Which of the following tools and/or techniques might be used by the business analyst to determine how the selection criteria requirement was missed?

Question9: Which of the following is a method for requirements change control?

Question10: A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example, Company A will designate technical staff to write and code the requirements and provide a testing team to test the new functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create project plans, schedule meetings, and provide meeting minutes.
In the scenario above, what is the role of the technical staff and testing team from Company A?

Question11: Which of the following actions will contribute most to the success of the initial stage of the project?

Question12: A business analyst is working with the project manager, company auditors, and project stakeholders to determine whether formal signoff should be required for the project. For which reason would the business analyst recommend formal signoff to the group?

Question13: A project that was going well for the last few months has encountered a situation-regulatory authorities have deemed that the project does not meet their requirements. Although regulatory requirements were identified during an earlier phase of the project, there is no substantial evidence to prove that the requirements were formally rejected.
This could have been avoided if:

Question14: A business analysis team has collected the main business requirements from the major stakeholders of a project. The team wants to be sure that each stakeholder has a clear understanding of the areas of analysis that will be in scope.
Which model should the team employ to ensure the most effective representation of analysis boundary?

Question15: In the first few weeks after a large implementation of a new web-based application, a critical report failed.
Further Investigation determined that a worker had been using a field that was not supposed to be used. This issue was not identified in testing.
Which technique could have prevented this problem from occurring?

Question16: A few months into a project, the business analyst determines that the costs are exceeding the perceived benefits. The business analyst wants to address the possible risks of having to cancel the product.
Which of the following documents should be used?

Question17: The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.
Which project artifact could the test team review to help identify acceptance criteria?

Question18: A business analyst is documenting the acceptance criteria to support a minor modification in a user portal.
The analyst submits the criteria for review, but it is deemed incomplete and returned.
What could have caused the documentation to be returned?

Question19: Requirements elicitation for a project is occurring. The marketing, acquisition, and production departments want to include specific requirements. The CEO has a requirement to deploy in three months.
Which of the following actions will have a greater influence on the project success?

Question20: The business analyst is conducting a feasibility study to understand how well a potential solution fits into the organization. What kind of feasibility assessment is the business analyst undertaking?

Question21: Company A would like to enter into a new market. The business analyst has been assigned to a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.
What should the business analyst recommend to the project manager?

Question22: A project affects the marketing unit and procurement unit. The project manager gives the business analyst an overview of the project for the first time.
What should the business analyst do immediately after the discussion?

Question23: Company A has been awarded a contract to finalize the development of a product that Company B was not able to finish. The business analyst is given a copy of the documentation left by Company B.
To which of the following documents should the business analyst pay the most attention to ensure the project succeeds this time?

Question24: After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides enough information to check if the requirement has been met.
Which of the following would work best in this case?

Question25: The business analyst has been assigned to a project which delivers functionality for a much larger solution.
The project has many requirements but has not received adequate funding. In addition, the stakeholders' views conflict.
Which tools and techniques should the business analyst use to maximize business value while establishing the requirements baseline?

Question26: The customer and the business analyst are collaborating in the development of a solution scope. It is important for the customer to:

Question27: The software developers have delivered a completed solution. The quality assurance team has passed the solution. What should the business analyst do next?

Question28: The business analyst is in the process of implementing a solution for a customer. The team is having difficulty confirming if certain requirements have been met.
What could have caused this issue?

Question29: The requirements baseline is ready for sign-off when the requirements are:

Question30: Which statement accurately depicts what changes can be made to requirements after they are baselined?

Question31: Projects have been managed well and completed on schedule and on budget. However, successful completion of the projects has not improved the company's performance and profitability.
Which of the following should have been implemented to ensure that the projects would improve the company's performance and profitability?

Question32: The business analyst is seriously concerned about the possibility of differing interpretations of data items mentioned in the requirements documents. Which course of action should the business analyst take to minimize the risk of misunderstanding?

Question33: The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders.
What should the business analyst do?

Question34: The following requirement was included in a business requirements document: "An API shall be built to send data back and forth from the accounting system to the customer relationship system so that name and address data can be synchronized." What should be done with this business requirement?

Question35: The quality function deployment is best suited to assist in the process of:

Question36: A business analyst and stakeholders have completed documentation of the acceptance criteria for the requirements of a new vehicle leasing database. A concern is raised that some of the key performance indicators may not validate the desired benefits of the implementation.
What should the business analyst do to ensure that the business need can be validated?

Question37: Change control systems include provisions to implement changes without formal review in the event of an emergency. When this provision is utilized:

Question38: How should a business analyst determine whether a solution satisfies business requirements?

Question39: The best way to ensure the integrity of requirements is to:

Question40: Which of the following tools will help facilitate the decision-making process when stakeholders do not agree on the value of an initiative?

Question41: Several interviews with stakeholders to develop an inventory management system in a new architectural environment have revealed a significant concern about system and architectural stability. In which tool should the business analyst include this attribute to ensure that the requirement meets the acceptance criteria?

Question42: A project was in the design phase when the team received news of a new regulatory mandate that affects the project. The requirements have already been approved and baselined. If the new requirements are not included, the company will be out of compliance and may face monetary penalties.
What should the business analyst do next?

Question43: What should a business analyst do after discovering that two solution requirements conflict?

Question44: A firm implements SharePoint and the business analyst creates the requirements to develop a business analysis repository. In the requirements, the analyst describes a detailed workflow that includes appropriate stakeholders receiving email notifications of certain activities. The SharePoint team needs to know which activities should trigger the notification workflow.
Which workflow trigger should the business analyst incorporate?

Question45: Which tool is the most appropriate to aid in development of measurable and actionable requirements for a new project?

Question46: Which of the following would be the best practice in product validation?

Question47: A company is awarded a contract to design and build a custom product. The contract references a detailed technical specification. What is the best action to take to ensure the design meets customer requirements?

Question48: A company is working on implementing a software application. They are converting their complex, in-house processes into the new system. The business analyst has been asked to analyze the processes.
Which technique should be followed?

Question49: A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?

Question50:
Which solution should be chosen according to the completed weighted-ranking matrix?

Question51: A company is working on the next big release of their best-selling product. The requirements will be validated through in-person validation sessions.
What would be the most viable technique to use in this scenario?

Question52: A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible.
Which activity should the business analyst initiate before beginning requirements elicitation?

Question53: The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and with a lean budget.
What should the team do to reduce the risk of rework?

Question54: Prior to the design phase, the project team needs to conduct a requirements review with the customer. To prepare for the review, it would be best for the team to:

Question55: The business analyst wishes to clarify the project's key business drivers and ensure that requirements can be prioritized to provide maximum business value. Which question should the business analyst ask of stakeholders to help obtain this clarification?

Question56: Which document best provides the boundaries for product development?

Question57: After conducting a brainstorming session with a group of project participants, the business analyst feels that the elicited requirements are biased. Which tool or technique could be used to gain an objective, first-hand insight into tasks and activities that are difficult to describe?

Question58: An organization is evaluating the possibility of conducting business internationally. Which factors should be investigated at the onset of the initiative?

Question59: The project team is working on the requirements specifications for a new product. The team reached a decision on which requirements will be included in the next release. A third of the stakeholders endorse one approach while no other approach achieved more than a quarter of the vote.
Which decision role was used?

Question60: A business analyst has received a test result report that shows evidence of defective functionality. The business analyst checks the test result again and verifies that the functionality behaves according to the requirements.
At this point, the business analyst should first:

Question61: What is a standardized, effective, and efficient way to manage changes to project documentation?

Question62: A company is developing a new e-commerce platform to enter a new market segment. Development is well under way when the government issues a new set of regulations.
Which course of action should the business analyst take?

Question63: A financial company deployed a new online product to their customers to invest in the stock market. The company notices a problem regarding financial calculations and starts the problem analysis. The company discovers that the new rules for taxes and fees were not implemented.
This problem could have been avoided by:

Question64: What are some of the components of a requirements management plan?

Question65: A business analyst is conducting a cost-benefit analysis of potential solution options. The stakeholders have indicated that the estimated growth rate is very important to them.
Which technique will allow the business analyst to determine this information?

Question66: A business analyst is working on a project's acceptance criteria. In an early collaboration with the company's stakeholders, the business analyst identified several user groups within the company: "Purchaser," "Shipper,"
"Customer," and "Agent." These user groups
categorize stakeholders with similar needs and create a detailed narrative.
Which technique did the business analyst use for evaluating the solution's acceptance criteria?

Question67: A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline.
The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.
Which tool or technique could have been used by business analyst to avoid this situation?

Question68: The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.
Which course of action should the business analyst take?

Question69: Which of the following techniques contrasts the current and desired business views to analyze possible business changes?

Question70: A company wants to improve the service to its customers by reducing complaint response time by 40%. To achieve this goal, it is necessary to redesign and optimize their internal processes and support it with a new product. The client thinks that disruption and short-term loss of productivity is inevitable.
Where can the business analyst best reflect the intangible costs associated with this change?

Question71: After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need.
Which approach best aligns with the business need for this organization?

Question72: A business analyst conducts an initial review to define scope. The analysis includes the review of the business case, project goals, and objectives to obtain the necessary and required context. Based on that information, the business analyst determines that this is a large project with multiple interfaces which could cost the company money that was not initially included in the budget.
What characteristics of the project are needed to determine the approach so that the business analyst can validate whether they will need to have a discussion about the budget?

Question73: During a requirements workshop, sponsors and managers from different departments express varying points of view and priorities about the product's functions and requirements. The business analyst struggles with facilitating the group to reach an agreement.
What should the business analyst have defined to avoid this?

Question74: The business analyst has worked with the stakeholders to capture their views of organizational improvement for the company. It would be best to align these with the:

Question75: In order to reduce product and project risk for a large, complex project, a business analyst is asked to help develop a change process that includes formal authorization and tracking throughout the life cycle of the project. The business analyst needs a capability that will help ensure that the product conforms to approved requirements, changes can be documented, and the status of each change can be reported.
What should the business analyst use?

Question76: For a large, highly complex project with significant risk, which elicitation technique should be used to analyze input to and output from the product?

Question77: How can a business analyst show progressive iterations of product development to stakeholders after the requirements baseline has been approved?

Question78: Which of the following can be used to determine if requirements align to the product's objectives?

Question79: After implementation of the product, the customer reports defects. What is the best course of action to take?

Question80: A business analyst is working on a highly complex project and has elicited a large number of requirements from stakeholders in several departments. Due to the large number of requirements, the stakeholders have determined that they would like to prioritize them to minimize a potentially large scope.
Which technique could the business analyst use to manage requirements?

Question81: Which tool should be used to improve the communication of product needs with the stakeholders and to improve their understanding?

Question82: A business analyst is trying to complete the requirement documentation of a project and finds that the developers have started development. The business analyst should first facilitate the:

Question83: After analyzing a set of requirements documents, it is determined that the requirements are not yet ready for peer review. This was most likely caused by:

Question84: A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.
The business analyst tells the stakeholder that the requirement status was changed to "deferred " What could have prevented the stakeholder from being surprised about the status change?

Question85: A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.
What is the most effective way to manage this situation?

Question86: A key component of the business analyst's role during acceptance testing is to:

Question87: During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis. To avoid this situation and minimize impact on the project, the user should have been:

Question88: A national company with offices in every state in the country has deployed a solution to allow employees to view their health benefits online. The business analyst on the project team is validating solution results to assess whether or not the solution has achieved the desired business result.
Which is the best technique to gather information from employees regarding their satisfaction with the solution?

Question89: How can a SWOT analysis help when deciding between several possible options to address a business problem?

Question90: What is one benefit of documenting the change control process?

Question91: A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.
Which type of requirements are these?

Question92: In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.
What task should the business analyst perform in order to identify these impacts?

Question93: A business analyst is assigned to the lead analyst role for a project. This project is one of the largest in the history of the company and includes several components and complex interfaces. The system in development will be used by a wide variety of stakeholders.
Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?

Question94: A business analyst is working on a project to implement a new call management system for a help desk. They expected the average time interval to answer a call to decrease over time, but the interval has increased instead.
Which technique should the business analyst use to investigate the problem?

Question95: A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with the enhancement?